What sets the date is usually one item’s lead time.

Each constraint on an existing hall has a relief, and each relief has a lead time. These are the ranges the engine uses when it has no quotation of your own. They are ranges from a reference library, not quotations, and a date built on one is labelled as resting on an assumption, not presented as a date.

ConstraintDomainIndicative lead timeWhat the cost figure for the relief rests on
Firm supply (grid import and behind-the-meter)electrical30 to 260 weeksno priced relief in the library
Transformer capacityelectrical52 to 160 weeksE0, library default
Chilled-water plant capacitythermal24 to 60 weeksE0, library default
UPS capacity (protected load)electrical20 to 52 weeksE0, library default
Achievable facility water temperaturethermal20 to 52 weeksE0, library default
Busway ampacityelectrical16 to 44 weeksE0, library default
Rack feed / tap-off ratingelectrical12 to 40 weeksE0, library default
CDU capacity at site conditionsthermal16 to 40 weeksE0, library default
Floor loadingphysical12 to 40 weeksno priced relief in the library
Hydraulic flow capacitythermal12 to 36 weeksno priced relief in the library
Cooling architecture per-rack capabilitythermal12 to 36 weeksno priced relief in the library
Residual air load removal per rackthermal10 to 30 weeksE0, library default
Available rack positionsphysical4 to 20 weeksno priced relief in the library

How to read this

  • A wide range means the item is uncertain, not that the table is vague: the spread between the low and the high is the uncertainty.
  • The longest range among the items your hall needs sets the date, because items procure in parallel.
  • Replace a range with a quotation and the date tightens, and its evidence class improves. See evidence classes.
  • Supplier lead times move; a range here is not a promise that anyone will deliver inside it.