Reference Project (synthetic) · hall DH-02 · issued 2026-09-14 · ref REF-TND-01
This package procures the works required to relieve Busway ampacity in hall DH-02. In the capacity model for this hall that constraint is what limits deployable rack count; relieving it moves the hall from 12 to 22 racks, and it is part of a programme that reaches 62 racks in total.
Duties in section 3 are sized for the end state of 62 racks of NVIDIA GB300 NVL72 — the hall this relief is part of delivering — not for the 10 rack(s) this single step unlocks on its own. Nobody buys plant for a marginal rack.
In the capacity model this step moves the hall from 12 to 22 racks; the full ladder reaches 62.
Every numeric requirement is derived from the capacity model and names the constraint it came from. Nothing here specifies a make or a model: we state the duty and the interfaces, the supplier proposes the equipment, and we take no margin on it.
The budget figure is our modelled estimate, not a price. It is stated so the client can see whether a response is in the right universe, and it carries its own evidence class.
Included in this package:
Explicitly excluded. Listed rather than omitted, because an unstated exclusion is a gap somebody discovers on site:
Obligation words carry their usual tender meaning: shall — non-compliance disqualifies the response; should — scored, not disqualifying; may — stated for context.
| Ref | Clause | Obl. | Value | From constraint |
|---|---|---|---|---|
| E-10 | Busway continuous ampacity | shall | 1,990 A (E3) | busway_ampacity |
| E-11 | Phasing and outage | shall | — | busway_ampacity |
| E-12 | Tap-off provision | shall | — | busway_ampacity |
| C-01 | Price basis | shall | — | commercial |
| C-02 | Validity | shall | — | commercial |
| C-03 | Response schedule | shall | — | commercial |
Every numeric requirement names the constraint it was derived from. A requirement nobody can trace back to a physical limit is one somebody invented.
**E-10 — Busway continuous ampacity** (shall). Each busway run shall have a continuous ampacity not less than the figure stated, at the hall's design ambient and installed configuration.
*Verification:* Type test certificate to the applicable standard, with derating basis stated.
**E-11 — Phasing and outage** (shall). The programme shall allow replacement run by run with the hall in service. The response shall state the outage window per run.
*Basis:* Live tenancy in the hall during the works.
*Verification:* Method statement and programme.
**E-12 — Tap-off provision** (shall). Busway shall accept tap-off units at the density required by the rack pitch stated in the response schedule.
*Basis:* Hall aisle configuration; 62 positions to be fed.
*Verification:* Layout drawing.
**C-01 — Price basis** (shall). Prices shall be delivered and installed, excluding VAT, in EUR, with exclusions listed separately.
*Basis:* Comparability. Four quotations on four bases cannot be evaluated.
*Verification:* Completed response schedule.
**C-02 — Validity** (shall). Prices shall remain valid for not less than 60 days.
*Basis:* The evaluation and approval cycle on a capital item of this size.
*Verification:* Stated on the quotation.
**C-03 — Response schedule** (shall). The response schedule in section 6 shall be returned completed. An incomplete schedule will not be evaluated.
*Basis:* Every figure in it feeds a comparison the client can check. A bid that answers a different question cannot be compared with one that answers this one.
*Verification:* Returned document.
Price is one criterion of five. The item being bought exists to unlock compute on a date: a response that is cheaper and materially slower is the expensive one, and the weighting says so.
| Ref | Criterion | Weight | What moves it |
|---|---|---|---|
| C1 | Compliance with the mandatory duty | 35% | Every 'shall' requirement met, at the site conditions stated. A duty quoted at a reference condition rather than at ours scores nothing. |
| C2 | Delivered programme | 30% | Weeks to site and to energisation, and which long-lead item governs. Assessed against what the item does to the energisation date. |
| C3 | Price | 20% | Delivered capex, and price per kW actually unlocked rather than price per unit of equipment. |
| C4 | Installation in a live hall | 10% | Outage duration per run or per unit, and the method statement. |
| C5 | Evidence quality | 5% | Test certificates and selection outputs at our conditions, rather than datasheets at reference conditions. |
Weights total 100.
Return these figures in these units. They feed a comparison the client can check line by line, which is only possible if every response answers the same question.
| Field | Unit | Required | Note |
|---|---|---|---|
| Delivered price, excluding VAT | EUR | yes | Delivered and installed. State exclusions separately. |
| Weeks from order to delivered on site | weeks | yes | |
| Weeks from delivery to energised | weeks | no | |
| Outage required per unit or per run | hours | no | |
| Duty achieved at the site conditions stated | kW or A | no | At OUR conditions. A figure at a reference condition is not a bid. |
| Price validity | days | no |
Machine-readable template: `gridforge spec … --template` writes a JSON file with these keys, which `gridforge bids` reads back.
Every number in this report carries an evidence class. The class of a computed number is never higher than the weakest of its inputs, so a model applied to measured data yields a modelled number and never a measurement.
| Class | Meaning |
|---|---|
| E0 | assumed |
| E1 | modelled |
| E2 | simulated |
| E3 | estimated |
| E4 | validated against test data |
| E5 | supplied by the client (not measured or surveyed by us) |
| E6 | field-validated |
| E7 | observed in operation |
E5 means supplied by the client — a declared rating, contract term or design value, or the client's own data as given. It is not a measurement we made, and it has not been verified by a site survey.
| Quantity | Evidence | Model | Digest |
|---|---|---|---|
| busway and tap-off works, per run | E0 | costs.scaled_relief | 8bca5c542732 |
| busway and tap-off lead time | E0 | input | 74ff17170551 |
| required busway ampacity per run | E3 | spec.busway_ampacity | 584d4571c5b5 |
| required busway ampacity per run | E3 | spec.busway_ampacity | 584d4571c5b5 |