Walkthrough

How much AI compute can DH-02 carry?

Capacity and density envelope · target platform NVIDIA GB300 NVL72 · 5 architectures compared

13 constraints across electrical, thermal and physical domains, solved over one model of this hall. The envelope is the minimum; the binding constraint is the one that produced it.

Every figure here comes from the same solved model as the written study, where each carries its evidence class and range. This deck shows them rounded and without the labels, so read it as modelled, not measured.

The answer

Rack feed / tap-off rating

platform needs 205 [174–236] A (E0) per rack; installed tap-offs rated 63 A (E5).

Deployable today
0
racks, as the hall stands
After the ladder
62
racks · Full DLC plus behind-the-meter supply
Time to full capacity
160
weeks (range 80–210) · set by transformer capacity

Reference Project (synthetic) · prepared 2026-09-14 · modelled, not measured

What stops it

The headroom ladder

Each row is what binds next, what moves it, and what that costs. Showing the first 8 of the 20 rungs taken; the full ladder is in the written study (section 2) and the final answer, 62 racks, is reached only after all of them.

#ConstraintRacksReliefCapexLead time
1Rack feed / tap-off rating0 → 0Higher-rated tap-off units (and busway if ampacity does not a… (no racks on its own: tied constraint)372,000 [186,000–744,000] EUR24 [12–40] weeks
2Residual air load removal per rack0 → 0Add in-row cooling or rear-door heat exchangers for the resid… (no racks on its own: tied constraint)558,000 [279,000–1,120,000] EUR20 [12–32] weeks
3Achievable facility water temperature0 → 8Adiabatic assist plus trim chiller on the high-temperature loop350,000 [175,000–700,000] EUR32 [20–48] weeks
4Transformer capacity8 → 8Replace / add transformer capacity (uprate ~60%) (no racks on its own: tied constraint)1,200,000 [600,000–2,400,000] EUR160 [80–210] weeks
5UPS capacity (protected load)8 → 12Add UPS modules / new UPS block768,000 [384,000–1,540,000] EUR30 [20–52] weeks
6Busway ampacity12 → 22Replace busway with 800-1000 A and new tap-off units450,000 [225,000–900,000] EUR36 [24–52] weeks
7CDU capacity (derated to site water temperature)22 → 25Add CDU capacity (one further unit per bank)180,000 [90,000–360,000] EUR26 [16–40] weeks
8UPS capacity (protected load)25 → 28Add UPS modules / new UPS block768,000 [384,000–1,540,000] EUR30 [20–52] weeks

Reference Project (synthetic) · prepared 2026-09-14 · modelled, not measured

When

Time to power

Reliefs run in parallel, so the racks unlocked by the first N steps arrive at the longest lead time among them. One item sets the date: transformer capacity.

8 racks at week 3262 racks at week 160016314662040801201608 racks · week 3262 racksweek 160 elapsed weeks — reliefs run in parallel racks energised

Capacity arrives in steps, not continuously — each step is a constraint relieved.

Architecture

The same connection, more compute

Every kilowatt the cooling architecture consumes is a kilowatt of contracted capacity that cannot be sold as compute.

Retained air, grid onlyRetained air, grid only: 0 racks0Rear-door heat exchangers, grid onlyRear-door heat exchangers, grid only: 0 racks0Hybrid DLC on retained plant, grid onlyHybrid DLC on retained plant, grid only: 26 racks26Full DLC, grid onlyFull DLC, grid only: 28 racks28Full DLC plus behind-the-meter supplyFull DLC plus behind-the-meter supply: 62 racks62

Reference Project (synthetic) · prepared 2026-09-14 · modelled, not measured

Cost

What it takes, and how well we know it

8 of 8 priced lines are library placeholders rather than quotations. That is why the accuracy class reads as it does — it follows the weakest line, not the average.

Indicative capex (lower bound)
≥ 18,800,000 EUR
a cost it needs has no price
Per kW of IT
2,250 EUR/kW
Accuracy class
Class 5 (order of magnitude)
-50% / +100%

Excludes IT hardware, migration and lost tenancy revenue.

Evidence

What nobody has measured yet

Intake is 83% complete. Each of these moves the answer and is currently a library default.

InputAssumedWhere it comes from
Installed CDU schedule[]CDU nameplates and the mechanical single-line diagram.
TCS target supply temperature30 [27–32] degC (E0)The platform vendor's reference design for the target rack.
Rear-door heat exchanger capacity per rack60 [20–80] kW (E0)The selected rear-door unit's datasheet at the site's water temperature and airflow.
All-in grid electricity pricelibrary placeholder of 140 EUR/MWh (E0)The supply contract, or 12 months of invoices divided by metered energy.
Discount ratenone: the lifecycle value is undiscountedThe client's hurdle rate.

Reference Project (synthetic) · prepared 2026-09-14 · modelled, not measured

Recommendation

Full DLC plus behind-the-meter supply

The same hall with on-site firm supply where the grid connection binds. The only scenario whose capacity is set by what can be built rather than by the queue.

Reference Project (synthetic) · prepared 2026-09-14 · modelled, not measured

Boundary

What this is, and what it is not

Nothing in this deck is a measurement of this asset unless it is labelled E5 or above.

1 / 9